KEY PERFORMING INDICATORS

Report for FY 2023-2024

Report for FY 2015-2021

INTRODUCTION

The following data is a compilation of data provided by the Pacific Power Utilities annual BenchmarkingΒ  Reports for Marshalls Energy Company for the Fiscal Year 2015 to 2021. As one can notice, certain yearsΒ  have no data, thus left blank, (2019).

As can be seen in MEC’s strategic foundations, MEC’s mission is to provide reliable, efficient energy toΒ  enhance the quality of life for the people of the Republic of the Marshall Islands.

MEC’s strategic map, as illustrated above, shows MEC’s priority areas that recognizes organizational capacity will enable business processes and financial stewardship which will enable for customer and stakeholder satisfaction.

As can be seen in the table above, MEC is a Medium size utility with a Peak Demand of 9.8 MW, with aΒ  total annual energy of 63,857 MWH, and a RE contribution of 1%.

The above data collected comes from paper written hourly log sheets completed by the power plantΒ  operators, engineers, and administration team. The collected data is entered in spreadsheets andΒ  processed into the charts and tables herein. The above bar chart represents Majuro’s Total MWhΒ  generated per year from 2013 till 2020. One can notice a slight increase from 2016 to 2017 to 2020.Β  Also, each line represents breakdown by feeder. Feeder 2 has the highest MWh, serving a largerΒ  population, then comes Feeder 1 , and Feeder 3.

1. GOVERNANCE INDICATOR

1.1 Key Governance Results

The composite governance score introduced in the 2012 Fiscal Year Report has again been utilised inΒ  each year’s power benchmarking exercise for the purpose of analysing if good governance mechanismsΒ  are delivering tangible benefits to utilities in the form of improved financial performance. The compositeΒ  score is comprised of the same weighted indicators as the 2012 Fiscal Year Report, determined fromΒ  relevant responses in the governance questionnaire using a governance scorecard (See table below).

Note: A good governance score results in full marks for each indicator, whilst a poor governance resultΒ  receives a zero for each applicable indicator. In regard to the indicator on Annual Reports beingΒ  completed within four months of the end of the reporting year, this has been used as a good practiceΒ  standard, but it is acknowledged that several utilities have agreements with their regulators that allowΒ  for longer periods for production of Annual Reports.

The table below shows Governance scores for MEC from 2015 to 2021. One can notice an increase inΒ  governance score in 2021.

2. DATA RELIABILITY

Figure 4.2 presents the data reliability category as assess by the utilities that responded. These areΒ  translated into aggregate reliability scores submitted by each of the utilities in order to rank the relativeΒ  reliability of the data that was submitted. These aggregate scores have furthermore been utilised as aΒ  weighting in this reporting in calculating the Composite Indicator for each year.

Data reliability for each year’s data submitted by MEC to PPA were as in table above.

3. KPI RESULTS

3.1 Introduction

This section provides performance results for the 2015 FY to 2021 FY. The results are comprised ofΒ  several KPIs, with each indicator graphically presented.

3.2 GENERATION INDICATORS

3.2.1 Load Factor

The Load Factor (LF) is the average load demand divided by the peak demand over a period. In thisΒ  report the period is the fiscal year and the LF is given for each electricity grid operated by the utility. TheΒ  LF is an indicator of the utilization of production capacity. Production capacity is maintained to provideΒ  for peak demand. A lower LF indicates a load profile with a greater peak compared to the average loadΒ  and a lower utilization of production capacity. A high LF implies a relatively flat demand profile andΒ  higher capacity utilization. This generally indicates an efficient use of production resources. However, aΒ  high LF could result from limiting peak demand by regular load shedding due to insufficient reliableΒ  production capacity. In this instance the high LF does not indicate an improved performance but isΒ  rather a symptom of insufficient reliable production capacity to meet the demand. The minimum LF

deemed acceptable is 50% while a benchmark of 80% is set for Pacific Island Utilities. Demand side management strategies, time of use tariffs, peak lopping and demand shifting strategies can be adoptedΒ  to limit the peak demand and improve the LF. This is expected to be an increasingly important activity inΒ  Pacific power sector policies.

MEC’s load factors for years 2017 to 2020 were above the benchmark of 80%.

3.2.2 Capacity Factor

Capacity factor (CF) is also an indicator of effectiveness in relation to the use of generation resources. ItΒ  is a similar measure to LF. Where LF measures average power as a percentage of maximum demand, CFΒ  measures average power demand as a percentage of installed firm capacity. The lower the CF theΒ  greater the production reserve capacity available to provide for demand when production units areΒ  taken out of service for maintenance purposes or for repairs due to faults. It also may suggest overΒ  investment in production capacity which situation is best avoided. A higher CF indicates a peak demandΒ  that approaches available production capacity. This may cause difficulties in scheduling maintenance forΒ  the generating plants and may result in load shedding during peak load periods when generators areΒ  taken out of service due to faults. The investment in production capacity is determine by the power

security policy adopted by the utility. Utilities may adopt a security policy of N-1 or N-2. N-1 productionΒ  capacity is the maintenance of sufficient production capacity to cater for the loss of the generating unitΒ  with the largest capacity in the fleet. Likewise, N-2 caters for the loss of the two largest units in the fleet.Β  The minimum production capacity is determined by the power security policy adopted based onΒ  experience concerning reliability, the cost of investment and expectations regarding the lifespan of theΒ  firm production equipment. Installing more capacity than required would be an inefficient way ofΒ  utilising a utilities financial resources, while, underinvesting may compromise the reliability of powerΒ  supply.

Too high a CF, risk having insufficient capacity to meet demand at all times

A low CF indicates over investment in capacity.

Pacific Benchmark >40%

MEC’s CF for 2018 and 2021 were above the benchmark of 40%.

3.2.3 Generation Labour Productivity

Generation Labour Productivity (GPL) is a measure of the total energy produced per full-time equivalentΒ  (FTEG). Benchmarking of GPL for comparable utilities in size, demand and generation asset types wouldΒ  indicate whether the utility production team is right sized. The average GPL for 2021 is 1.89 GWH. For

2020 the average was 1.3 GWH. The GLP for 2020 and 2021 is not comparable for the 2020 data did notΒ  include the GLP for GPA and EFL. GPA and EFL are the larger utilities in the PPA and as expected theyΒ  have a higher GLP than the smaller utilities and so have lifted up the average.

MEC’s GLP are shown in the above graph.

3.2.4 Specific Fuel Consumption DFO (kwh/Litre)

Specific fuel consumption (SFC) is a measure of the efficiency of fuel used for power generation utilizingΒ  diesel fired power generators, and is often reported in kWh/litre, kg/kWh or kWh/gallon. It is a criticalΒ  performance indicator because fuel costs accounts for the bulk of generation expenses in a typicalΒ  diesel-based power utility. Importantly, SFC refers to the efficiency of utility fossil fuel generation only – it does not include purchased energy from Independent Power Producers (IPPs). Furthermore, non diesel generation is not factored into this indicator. As power utilities transition away from fossil fuel based production of power to renewable resources, and more IPPs are engaged in the production ofΒ  energy, the impact of fossil fuel will factor less in the overall efficiency and costs of energy production.

The Benchmark for SFC is 4 kWh per litre. The lower the indicator the less efficient the operation of theΒ  diesel generator.

MEC’s SFC was at 4 kWh in 2015 and maintained at just below the benchmark of 4 kWh for subsequentΒ  years.

3.2.5 Specific Lubricating Oil Consumption

Specific Lubricating Oil Consumption (SLOC) is a measure of lubricating oil efficiency of usage by theΒ  diesel and HFO generating units and is determined by the number of kWh generated per litre ofΒ  lubricating oil consumed. The benchmark varies according to the size and condition of the diesel engine.Β  Lower lubricating oil efficiency can be attributed to poor maintenance, e.g. due to worn piston rings orΒ  leaks in the system. Reasonable values are about 500–700 kWh per litre for a 1 MW engine and 1,000– 1,300 kWh per litre for a 4–5 MW engine. SLOC much like the SFC will become less important as anΒ  indicator as the contribution to the energy produced is increased from renewable sources, especiallyΒ  from solar PV power plants.

Lubricating oil consumption for MEC has decreased over the years from 904 to 489.

3.2.6 Forced Outage

A forced outage is an unplanned outage (or generator downtime) that has been forced on the utility.Β  Unplanned outages are attributable to issues with generators that compelled the utility to take themΒ  out of service. In 2021, 9 utilities provided sufficient data for 18 grids. The average forced outageΒ  indicator for the 18 power grids is 0.3%. The Pacific benchmark is less than 3%.

MEC’s forced outage has decreased considerably from 26.9% to 4.2% from 2016 to 2018.

3.2.7 Planned Outage

Planned or scheduled outages measure the proportion of downtime for planned maintenance activitiesΒ  that require the plant to be shut down. It is a scheduled loss of generating capacity as a percentage ofΒ  installed capacity to generate energy. Planned maintenance of generating equipment is oftenΒ  compromised in Pacific Island utilities.Β 

Some reasons for this are; (1) insufficient firm reserve capacity to allow the extended shutdown ofΒ  generators due for scheduled maintenance, (2) a lack of spare parts in store leading to long downtimesΒ  awaiting for delivery of spares, and (3) lack of funds for major contracted service work. When theΒ  intervals between maintenance are extended, the probability that generators will break down increases.Β  The Pacific benchmark is below 3%. An indicator that is too low may indicate the lack of scheduledΒ  maintenance which if so would eventually result in a higher than expected force outage indicator.

3.2.8 Generation Operations and Maintenance (O&M) Costs

The indicator used is the expenditure on O&M for generating equipment per MWh generated,Β  expressed in USD.

3.2.9 Power Station Usage

This indicator measures the usage of power in % by the power station to generate electricity. Below 5%Β  is considered acceptable, and lower it is the better.

3.3 DISTRIBUTION INDICATORS

3.3.1 Network Delivery Losses

Network delivery losses are defined as the net generation minus electricity sold, divided by netΒ  generation, and expressed as a percentage. Net Generation is energy generated less the power stationΒ  auxiliary usage. For utilities that have a transmission network, this loss includes the transmission andΒ  distribution network losses. This is only true for utility members of the PPA who have transmissionΒ  network. For the other utility members who do not have a transmission network the Network DeliveryΒ  Losses is equal to the Distribution Losses. Therefore, in this report the Distribution loss is not presentedΒ  separately as in previous reports. The losses comprise technical and non-technical losses. TechnicalΒ  losses are mainly caused resistance in the network lines and cables which may be exacerbated byΒ  imbalances in the currents for each phase and high resistance joints in the distribution system. TheseΒ  depend on distribution voltages, loading, conductor material, physical dimensions and state ofΒ  conductors. Non-technical losses are those attributable to electricity used by a consumer but not paidΒ  for, including electricity theft, meter reading and accounting errors, unmetered connections, meteringΒ  errors, etc. This category should not include the use of electricity within the utility itself (other facilityΒ  use), free provision for street lighting, or electricity provided to the water and sewerage wasteΒ  management for utilities that are responsible for electricity, water and sewerage services. Inclusive ofΒ  transmission loss this indicator should be below 10% for power grids that have transmission systemsΒ  while for the smaller utilities this should be below 5%.

As can be seen in the graph above, MEC’s Network Losses is very high, well above the 10% benchmark.

3.3.2 Distribution Transformer Utilization

This indicator measures the transformer average load against the transformer capacity in megavoltΒ  amperes (MVA). It is calculated by dividing the total electricity sold by the total capacity of distributionΒ  transformers. High utilisation implies an efficient capital expenditure process for investing in distributionΒ  transformer capacity to meet the demands of customers. This process takes into consideration non coincident demand characteristics, demand growth and contingency requirements to maintain supplyΒ  security and reliability. Transformer utilisation in Pacific utilities is low. In 2002 a regional goal of 30%Β  was set.

The report noted that β€œthis can only be achieved in the long term because of the long lead timesΒ  required to improve usage of capital assets. For 2021 the range for TUF is 7% to 54%. The Benchmark isΒ  30%. It appears that the situation has not improved.

3.3.3. Distribution Reliability

This indicator looks at forced outage events per 100km of distribution line as a way of measuring theΒ  reliability of the distribution network. The average for FY 2021 is 21 events per 100 KM of distributionΒ  lines. The average for the utilities that report for the year 2020 was 29.

Ongoing maintenance to preserve the condition of infrastructure is key to improving reliability andΒ  customer service. The number of planned outage events reflect the maintenance carried out on theΒ  distribution network.

3.3.4 Customers per Distribution Employee

The number of customers per distribution employee full time equivalent is another indicator of labourΒ  productivity

3.3.5 Distribution O & M Expenses

The Distribution Operations and Maintenance O&M costs is the total expenses incurred in theΒ  operations and maintenance of the distribution network, in USD. This includes all vehicle operating costsΒ  and all other costs related to distribution operations. This total O&M cost is divided by the distributionΒ  line length.

3.4 SAIDI and SAIFI

3.4.1 System Average Interruption Duration Index (SAIDI)

SAIDI indicates the average duration of power outages experienced by customers and is measured inΒ  customer minutes. The results are shown in Figure 5.5.1 as Planned and Unplanned outages that haveΒ  resulted in power interruptions to customers. The categories based on the source of the interruptionΒ  are, planned and unplanned generation events, and planned and unplanned network events. For theΒ  utilities not included in Figure 5.5.1, the data was either not provided or appears to be faulty or is wellΒ  below the benchmark. The benchmark for Pacific Island utilities is for the total Planned and UnplannedΒ  SAIDI to be below 200 customer minutes.

Unplanned outages are calculated SAIDI minutes = (Total Customer Interruptions Duration InterruptedΒ  (cust hr) * 60 )/ (Average Number of Customers (connections)). The benchmark set by the PPA is 200Β  customer minutes. MEC’s data show that Dec 2020 had very high SAIDI over the benchmark limit, thenΒ  decreased considerably in the following months to acceptable numbers.

3.4.2 System Average Interruption Frequency Index (SAIFI)

SAIFI indicates the average frequency of power interruptions experienced by customers over the fiscalΒ  year. For small island utilities the power interruptions to customers caused by generation events can beΒ  significant compared to distribution network events. Figure 5.5.2 shows the Planned and UnplannedΒ  SAIFI for each utility. Again, those utilities not included have either not provided data, or the dataΒ  provided appears to be unreasonably high, or the index is well within the benchmark. The benchmarkΒ  for Pacific Island utilities is for the total of Planned and Unplanned SAIFI to be below the average of 10Β  events per customer.

SAIFI data for MEC for 2016 to 2018 are illustrated in the graph above. SAIFI numbers are still high asΒ  compared to the benchmark.

3.5 Financial Indicators

3.5.1 Tariff Impact

Conducting tariff analysis of Pacific utilities is highly complex due to the different tariff schedules andΒ  structures. This section therefore compares the impact of the tariff schedule applied to customers of

various categories. The monthly bills for a domestic or residential customers with a usage of 100 kWhΒ  and 200 kWh and 500 kWh is compared, ranked and graphed in ascending order. The same is done for aΒ  commercial customer with a usage of 1,000 and 5,000 kWh per month. For industrial customers theΒ  monthly electricity bill for a usage of 10,000 kWh per month is compared.

3.5.1.1 Residential Customer (200 kWh per month)

3.5.1.2 Commercial Customer (1,000 kWh per month)

3.5.2 Utility Cost Breakdown

The cost categories for which information was collected included hydrocarbon-based fuel andΒ  lubrication costs, duty on fuel and lubricating oil, generation O&M, labour and deprecation,Β  transmission and distribution O&M, labour and depreciation, and other overhead expenditure, duty,Β  taxes and miscellaneous costs. The percentage contributions of each component are presented for theΒ  utilities that reported sufficient data in Figure 5.7.4 below. Fuel and lubricating oil expenditure is theΒ  largest component in the utilities cost structure ranging from 24% to 72%.

3.5.3 Debt to Equity Ratio

The indicator used for the level of utility debt is the ratio of total liabilities to equity, expressed as aΒ  percentage (debt / equity). Borrowing to improve services may be justified, but a high debt-to-equityΒ  ratio places a utility in a vulnerable position. Some smaller utilities do not have access to debt fundingΒ  and rely on their government or grants from donors for large projects and so have no long-term debtΒ  obligations.

3.5.4 Return on Assets

The Rate of Return on Assets (RORA) is the return generated from the investment in the assets of theΒ  business. ROA indicates how efficient management is at using its assets to generate earnings. PacificΒ  power utilities generally do not earn commercial rates of return.

3.5.5 Return on Equity

ROE measures financial returns on owners’ funds invested. Results for ROE are shown in graph below.

3.5.6 Current Ratio

The current ratio measures the ability of business to pay its creditors within the next 12 months, i.e., theΒ  ability of the utility to meet its current liabilities from current assets. A current ratio above 1 is desirable.Β  A ratio below 1 implies that the utility is not able to cover for its current liabilities.

3.5.7 Operating Ratio

The operating ratio is a measure of how efficiently a business is operating, in this case, providingΒ  electricity service. It is determined by the Costs of Goods and Services (COGS) Including depreciationΒ  expenses divided by the revenue earned. An operating ratio below 100 indicates a profitable operation.Β  An operating ratio above 100 indicates that it is costing an organisation more to provide the service thanΒ  the revenue derived from the service.

3.5.8 Debtor Days

This indicator measures how long it takes, on average, for the utility to collect debts (receivables) owe toΒ  it. In 2021, the Pacific average was 95.14 days. In 2020 the average was 78.7 days and the average DD inΒ  2019 was 88 days. The Pacific benchmark is set at 50 days

3.5.9 Operating Profit

MEC’s Operating Profit increased from a deficit of $1.47 M in 2019 to increase in profit of $2M in 2020Β  and of $4.3 M in 2021. This shows that positive reforms of MEC have increased profit and cut down onΒ  expenses.

3.6 Human Resources & Safety Indicators

3.6.1 Lost Time Injury Duration Rate

The average for 2021 FY was 0.08 days per FTE employee, compared to 0.58 days for 2020 FY.Β  Unfortunately, only a limited of utilities responded making it difficult to draw any significant conclusions.Β  This is an area that may need improvements in monitoring and recording of incidents.

3.6.2 Lost Time Injury Frequency Rate

Only a limited number of utilities were able to provide sufficient data to determine the LTIFR.

3.6.3 Overall Labour Productivity

The Pacific average productivity in 2021 is 107 customers per Employee FTE. In 2020 the average wasΒ  123, and in 2019 FY, 94. A higher productivity is expected of larger utilities that operate with some economies of scale and are fully or partially privatise such as EEC, EFL and UNELCOΒ MEC’s productivity increased from 25 in 2015 to 2018 to 33 in 2021

3.7 Overall Composite Indicator

The overall composite indicator of utility performance was developed in 2011 to rank comparativeΒ  performances between utilities. Where gaps existed in the data submitted by some utilities it was notΒ  possible to calculate an aggregate score. The overall composite indicator is a simple indicator thatΒ  equally weights generation efficiency, capacity utilisation, system losses and overall labour productivity,Β  as derived from quantitative scores on a scale up to 100%. Table 5.9.1 ranks the utilities for which theΒ  full data was provided. The composite technical indicator reflects the heavy reliance of powerΒ  production on fossil fuels and its high impact on the production expenses. With the aggressive

pursuance of renewable energy production this indicator that is skewed to favour efficient fossil fuelΒ  production, will become less relevant going forward.

Performance Ranking of PIC Power Utilities in 2021

In 2021, MEC’s score was 33%, performed low compared to other Pacific Power Utilities. Low score isΒ  attributed to high system losses, and low overall labor productivity.

The overall composite indicator was scaled with a maximum score of 4.0 in the past benchmarkingΒ  reports up to 2019, it’s the same as percentage but with a maximum score of 4.0 instead of 100%. It’s a simple indicator that equally weights generation efficiency, capacity utilisation, system losses andΒ  overall labour productivity, as derived from quantitative scores on a scale up to 4.0. Overall, this wasΒ  considered to be a valid assessment of technical performance.

MEC’s composite score for three years assessed for 2015 was low 2.1, lower in 2018 with a score of 1.6Β  and a score of 1.3 in 2021.